A new Kier report drawing on major government programmes identifies measurable improvements in productivity, quality and delivery certainty, while calling for longer-term, more integrated delivery models.
Kier has reported a 47% improvement in productivity, 40% improvement in quality and 15% improvement in delivery certainty through industrialised construction approaches across major public sector programmes.
Its report, Lessons from the Construction Playbook: Industrialisation in Action, draws on work supporting the Ministry of Justice‘s New Prison Programme, NHS New Hospital Programme, Defence Infrastructure Organisation’s Single Living Accommodation Programme and Department for Education construction frameworks.
Measuring the delivery gains
The analysis identifies delivery 22% faster than traditional, non-systemised approaches, alongside 43% fewer technical queries per 100 documents and a 41% reduction in construction waste per 100 sq m.
On prison projects, Kier reports that 74% of houseblock design and 60% of overall project design have been standardised. Digital tracking supported a 99.3% precast quality rate, while embodied carbon in precast concrete was reduced by 14.9% against the Fosse Way prison baseline.
The report also identifies 15% fewer quality issues per 100 sq m and states that 100% of New Prison Programme projects were completed to budget and schedule.
Conditions for repeatable delivery
Kier links these outcomes to principles set out in the Construction Playbook, including early supply chain engagement, outcome-based specifications, standardisation and longer-term contracting.
Andrew Dewdney, Head of Industrialisation at Kier, said:
“What we’ve found is that the greatest benefits come when industrialisation is viewed as more than a construction methodology. It is about creating the conditions for continuous improvement through repeatable requirements, integrated supply chains and long-term programme thinking.”
The report calls for standardised outcome measures, closer alignment between clients and supply chains, and a broader assessment of productivity that captures certainty, quality, waste, carbon performance and workforce stability alongside cost.
Source & image credit: Kier Group