The New Hospital Programme is tightening its industrialised approach around standardisation, alliance procurement and repeatable components as it prepares to move the next wave of hospital schemes into delivery.

The New Hospital Programme is trying to do something the NHS has rarely achieved at this scale – move from one-off hospital delivery to a repeatable production model. With Mace and Turner & Townsend leading the Health Delivery Partnership since February 2025, the focus is now on turning Hospital 2.0 from programme language into a working delivery system across 46 major projects stretching into the early 2040s.

At the centre of that shift is a standardised model intended to reduce risk, improve predictability and create economies of scale across layouts, components and processes. The programme’s leadership says this is not just about offsite products. It is about industrialisation at programme level – from business cases and commercial structures through to in-room MEP modules, risers, facades, partitions, doors and ensuite bathrooms.

Alliance model moves to the front

The next phase of schemes will be delivered through the Hospital 2.0 Alliance, with Tier 1 contractors brought into a model based on Project 13 principles. The aim is to rebalance risk and pull major contractors back into a market many had left. Darren Colderwood said: “The commercial model has been set up in order to make it attractive, to balance risks sensibly.” Doug Baldock added that the new approach has already helped attract contractors back into the sector.

Standardisation under pressure

The programme’s leadership is also trying to hold trusts to the core model as schemes progress through design. That matters because the value of Hospital 2.0 depends on repeatability. Darren Laybourn said: “There is a desire to cut the cost to get to the optimum level. At the same time, we want to increase predictability and reduce uncertainty.” Baldock was more direct on the risk to that ambition: “The biggest challenge is getting the trusts to hold the line so that when they get to RIBA stages 3 and 4, we can embed the products.”

Design prototyping is already being used to de-risk the pipeline, including a prototype ensuite patient room built by Reds10 in Driffield. The seven RAAC hospitals in Wave 1a are expected to be the first real test of the model, with starts planned for late 2027 or early 2028. Alongside that, the programme is using a pipeline intelligence portal to track component demand and is preparing a skills academy to reduce supply chain pressure in constrained regional markets.

The New Hospital Programme projects

Already completed (opened between 2021 and 2024)

  • Hospital Northern Centre for Cancer Care
  • Royal Liverpool Hospital
  • Sycamore Unit at Northgate Hospital
  • Brighton 3Ts Phase 1
  • Greater Manchester Trauma Hospital
  • Dyson cancer Care
  • Midland Metropoliotan University Hospital

Wave 0 – under way

  • Alumhurst Road Children’s Mental Health Unit, Dorset (Kier Construction)
  • Royal Bournemouth Hospital, Dorset (Integrated Health Projects (Vinci-Sir Robert McAlpine))
  • St Ann’s Hospital, Dorset (Kier Construction)
  • Dorset County Hospital, Dorchester (Tilbury Douglas)
  • CEDAR Programme (Sir Robert McAlpine)
  • Oriel Eye Hospital (Bougues (UK))
  • National Rehabilitation Centre (Integrated Health Projects)

Wave 1a – RAAC hospitals (to be delivered through Hospital 2.0 Alliance)

  • West Suffolk Hospital, Bury St Edmunds (RAAC) £1 billion to £1.5 billion
  • Hinchingbrooke Hospital (RAAC) £501 million to £1 billion
  • James Paget Hospital, Great Yarmouth (RAAC) £1 billion to £1.5 billion
  • Queen Elizabeth Hospital, King’s Lynn (RAAC) £1 billion to £1.5 billion
  • Leighton Hospital (RAAC) £1 billion to £1.5 billion
  • Airedale General Hospital (RAAC) £1 billion to £1.5 billion
  • Frimley Park Hospital (RAAC) £1 billion to £2 billion

Wave 1b (to be delivered through Hospital 2.0 Alliance)

  • Milton Keynes Hospital £500 million or less
  • Hillingdon Hospital, north-west London £1 billion to £1.5 billion
  • North Manchester General Hospital £1 billion to £1.5 billion

Wave 1c (more developed schemes, being delivered under ProCure 13)

  • Poole Hospital, Dorset (integrated Health Projects) £500 million or less
  • Derriford Emergency Care Hospital, Plymouth (Mace-Willmott Dixon) £500 million or less
  • Cambridge Cancer Research Hospital (Laing O’Rourke) £500 million or less
  • Shotley Bridge community Hospital, Durham (Tilbury Dougals) £500 million or less
  • Women and Children’s Hospital, Cornwall (not yet awarded) £500 million or less
  • Brighton 3Ts Hospital (Laing O’Rourke) £500 million or less

Wave 2

  • Leeds General Infirmary £1.5 billion to £2 billion
  • Specialist Emergency Care Hospital, Sutton £1.5 billion to £2 billion
  • Whipps Cross University Hospital, north-east London £1 billion to £1.5 billion
  • Princess Alexandra Hospital, Harlow £1.5 billion to £2 billion
  • Watford General Hospital £1.5 billion to £2 billion
  • Leicester Royal Infirmary, Leicester General Hospital and Glenfield Hospital £1 billion to £1.5 billion
  • Kettering General Hospital £1 billion to £1.5 billion
  • Musgrove Park Hospital, Taunton £501 million to £1 billion
  • Torbay Hospital £501 million to £1 billion

Wave 3

  • Charing Cross Hospital and Hammersmith Hospital, London £1.5 billion to £2 billion
  • North Devon District Hospital, Barnstaple £1 billion to £1.5 billion
  • Royal Lancaster Infirmary £1 billion to £1.5 billion
  • St Mary’s Hospital, north-west London £2 billion or more
  • Royal Preston Hospital £2 billion or more
  • Queen’s Medical Centre and Nottingham City Hospital £2 billion or more
  • Royal Berkshire Hospital, Reading £2 billion or more
  • Hampshire Hospitals £2 billion or more
  • Eastbourne District General, Conquest Hospital and Bexhill Community Hospital £1.5 billion to £2 billion

Source: Hospital 2.0: Industrialising healthcare construction via Construction Management

Emily King, Industrialisation Consultant at NHP, is speaking at the Industrialised Construction Conference 2026, bringing the New Hospital Programme perspective into a wider programme focused on delivery at scale.

Book now to hear from the clients, consultants and delivery leaders driving this agenda forward.

Banner advertising the Industrialised Construction Conference

Leave A Comment

Share This Story